Sacramento's own fee estimate (revised July 12, 2026) puts city fees for a new 749 sq ft ADU at about $5,272 and a 750 sq ft ADU at about $10,624, because three impact fees switch on at 750 sq ft. A 1,200 sq ft ADU runs about $14,843 before county sewer, school and tap fees. The city also runs a pre-approved detached ADU plan program under AB 1332.
Last verified: November 10, 2026
Sacramento publishes something most cities do not: a line-by-line ADU fee estimate. It shows the most useful number on this page. Adding one square foot, from 749 to 750, roughly doubles the city’s fees, because three impact fees that are waived for small ADUs kick in at 750 sq ft. If you are designing in Sacramento, that line should shape the floor plan.
What Changed for Sacramento ADU Permits in 2026
The city revised its ADU fee estimate (Form CDD-0419) on July 12, 2026, with a construction valuation of $170.80 per sq ft. Statewide, SB 543 took effect January 1, 2026: ADU size is measured by interior livable space, the completeness check is due within 15 business days, and resubmittal comments are limited to items from the first check. That interior-space rule matters at the 750 sq ft line.
Sacramento ADU Fees by Size
From the city’s estimate for new construction:
| Fee | 749 sq ft | 750 sq ft | 1,200 sq ft |
|---|---|---|---|
| Building permit | $1,267.56 | $1,268.71 | $1,790.36 |
| Building plan review | $532.37 | $532.86 | $751.95 |
| Fire (admin, inspection, plan review) | $730.00 | $730.00 | $730.00 |
| Planning (inspection and review) | $789.00 | $789.00 | $789.00 |
| Construction excise tax | $590.21 | $591.00 | $945.60 |
| Park development impact fee | Waived | $2,617.50 | $4,188.00 |
| SAFCA development impact fee | Waived | $1,575.00 | $2,520.00 |
| STA mitigation fee | Waived | $1,154.64 | $1,415.76 |
| Estimated total (all lines) | $5,271.90 | $10,624.40 | $14,842.50 |
The totals include smaller lines not shown here (Public Works and Utilities deposits, technology, general plan, recycling, business tax and others). They exclude county regional sanitation and sewer development fees, school impact fees, water and sewer tap fees, and any extra hourly review ($216 an hour for building, $263 for planning, $260 for fire).
How the Sacramento ADU Permit Process Works
- Decide the size first. Under 750 sq ft of interior livable space keeps the park, SAFCA and STA impact fees off the bill.
- Choose a plan. The city’s AB 1332 program pre-approves detached ADU plans from designers; they still need site-specific zoning approval. The city also lists shelf-ready plans on its ADU Resource Center.
- Submit to Community Development for planning and building review.
- Confirm county and school fees. Regional San and sewer development fees come from Sacramento County, and school fees go to the school district.
- Build and pass inspections.
Frequently Asked Questions
How much are ADU permit fees in Sacramento?
About $5,272 in city fees for a new 749 sq ft ADU, $10,624 at 750 sq ft and $14,843 at 1,200 sq ft, per the city’s July 2026 estimate, before county sewer, school and tap fees.
Why do fees jump at 750 square feet?
Under state law, impact fees cannot be charged on ADUs under 750 sq ft. At 750 sq ft and up, Sacramento’s park, SAFCA and STA fees apply, adding about $5,350.
Does Sacramento have pre-approved ADU plans?
Yes. The city runs an AB 1332 program that pre-approves detached ADU plans; a project using one still needs site-specific zoning approval.
How long does a Sacramento ADU permit take?
State law requires a decision within 60 days of a complete application, or 30 days for a detached ADU using a pre-approved plan.
Sources
- City of Sacramento, Accessory Dwelling Unit Fee Estimate, Form CDD-0419 (revised July 12, 2026): https://www.cityofsacramento.gov/content/dam/portal/cdd/Building/Forms/CDD-0419_Accessory-Dwelling-Unit-Fee-Estimate.pdf
- City of Sacramento, Preapproved Accessory Dwelling Units (AB 1332): https://cityofsacramento.gov/community-development/building/building-programs/preapproved-adu-program-ab1332
For the state rules, see our California ADU law guide. For budgets, see our Sacramento ADU cost guide and our Sacramento ADU builders.
This page is general information, not legal advice. Confirm current fees with the City of Sacramento before you design or apply.
Nearby cities
Permit rules and timelines in other California cities we cover.
Berkeley
8 to 12 weeks
Campbell
5 to 14 weeks
Cupertino
4 to 20 weeks
Long Beach
Same day to 8 weeks
Los Altos
3 to 9 weeks
Los Angeles
4 to 16 weeks
Los Gatos
4 to 16 weeks
Riverside
1 to 12 weeks
San Diego
60 days after a complete application (state deadline)
San Francisco
60 days after a complete application (State program)
San Jose
Same day (preapproved plan) to 26 weeks (custom)
Santa Clara
5 to 16 weeks
Saratoga
6 to 18 weeks
Sunnyvale
Over-the-counter review by appointment for single-story projects of 800 sq ft or less; otherwise 21-day first review and 14-day resubmittals, plus 2 to 4 weeks for the Planning permit on new ADUs over 800 sq ft