San Francisco runs two ADU programs. The State program is ministerial, with a 60-day review and a 4-foot side and rear setback; the Local program offers waivers for rear yard, open space and density, but a waiver on a lot with a rental unit puts the ADU under rent control. The city says fees run about 6 to 9% of construction cost, and adding a unit typically costs at least $125,000.
Last verified: November 10, 2026
The first decision in a San Francisco ADU is not the design. It is which of the city’s two programs you file under, and you usually cannot switch later without starting over. The State program is faster and more predictable. The Local program can fit an ADU where the state rules would not, but the price of a waiver can be rent control on the new unit.
What Changed for San Francisco ADU Permits in 2026
The Planning Department updated its State ADU fact sheet on August 11, 2025, and DBI’s ADU resource sheet on October 6, 2025. State law moved on January 1, 2026: SB 543 measures size by interior livable space and requires a completeness check within 15 business days. Appeals of State-program ADU permits have been barred for applications filed since January 1, 2024.
State Program vs Local Program
| State ADU program | Local ADU program | |
|---|---|---|
| Review | Ministerial, 60 days from a complete application, no CEQA, no neighborhood notice or discretionary review | Discretionary; Planning reviews before DBI |
| Number on a single-family lot | 1 on lots with 4 or fewer units | Generally 1 |
| Size | 850 sq ft (studio or one-bedroom), 1,000 sq ft (two-plus bedrooms), or 50% of an existing house if greater | Based on buildable area, same caps |
| Height (detached) | 16 ft; 18 ft near major transit, plus 2 ft for a matching roof | Generally 16 ft by zoning |
| Setbacks | 4 ft side and rear; none when rebuilding an existing structure in place | Zoning district setbacks; generally 4 ft for detached |
| Waivers | Not a waiver program | Rear yard, open space, partial exposure and density waivers |
| Rent control | Deed restrictions may apply | A waiver on a lot with a rental unit requires a Costa Hawkins agreement, putting the ADU under rent control, plus a deed restriction barring separate sale and short-term rentals |
Both programs bar ADUs where an owner move-in eviction happened in the past 5 years or another no-fault eviction in the past 10 years. Impact fees are the same in both: none for ADUs under 750 sq ft or on lots with 3 or fewer existing units.
How the San Francisco ADU Permit Process Works
- Pick the program and confirm eligibility, including eviction history.
- For the Local program, file a project application with Planning and get a Planning approval letter. Post the required notice at least 15 days before applying.
- Clear pre-application items that apply: historic review, SF Fire flow requirements, Public Works and Public Health permits, and DBI address validation.
- Choose a Full or Site permit. Most ADUs use a Full permit, and the choice cannot be changed without resubmitting.
- Submit electronically with the ADU screening form, tolling declaration and Rent Ordinance affidavit, then pay the filing fee to start review.
- State program projects go to the Permit Review Roundtable, which has no extra fee.
- Pay the issuance fee and school fees, then build and pass inspections.
Frequently Asked Questions
How long does an ADU permit take in San Francisco?
Under the State program, the city must act within 60 days of a complete application. The Local program is discretionary and generally slower.
How much are ADU permit fees in San Francisco?
The city estimates fees at about 6 to 9% of construction cost, and says adding a unit typically costs at least $125,000. There are no impact fees for ADUs under 750 sq ft or on lots with 3 or fewer units.
Will my San Francisco ADU be rent controlled?
It can be. If you use a Local program waiver on a lot with a rental unit, a Costa Hawkins agreement puts the ADU under rent control.
Can I build an ADU after evicting a tenant in San Francisco?
Not soon after. Neither program allows an ADU where an owner move-in eviction happened in the past 5 years or another no-fault eviction in the past 10 years.
How big can an ADU be in San Francisco?
850 sq ft for a studio or one-bedroom and 1,000 sq ft for two or more bedrooms, or 50% of an existing house if that is larger, under the State program.
Sources
- City and County of San Francisco, Get a building permit for an accessory dwelling unit: https://www.sf.gov/get-a-building-permit-for-an-accessory-dwelling-unit-adu
- San Francisco Planning, ADU programs comparison (State ADU Fact Sheet, August 11, 2025): https://SFPlanning.org/sites/default/files/documents/adu/ADU_programs_comparison_chart.pdf
For the state rules, see our California ADU law guide. For budgets, see our San Francisco ADU cost guide.
This page is general information, not legal advice. Confirm current rules with DBI and the Planning Department before you design or apply.
Nearby cities
Permit rules and timelines in other California cities we cover.
Berkeley
8 to 12 weeks
Campbell
5 to 14 weeks
Cupertino
4 to 20 weeks
Long Beach
Same day to 8 weeks
Los Altos
3 to 9 weeks
Los Angeles
4 to 16 weeks
Los Gatos
4 to 16 weeks
Riverside
1 to 12 weeks
Sacramento
60 days after a complete application (state deadline); 30 days with a pre-approved plan
San Diego
60 days after a complete application (state deadline)
San Jose
Same day (preapproved plan) to 26 weeks (custom)
Santa Clara
5 to 16 weeks
Saratoga
6 to 18 weeks
Sunnyvale
Over-the-counter review by appointment for single-story projects of 800 sq ft or less; otherwise 21-day first review and 14-day resubmittals, plus 2 to 4 weeks for the Planning permit on new ADUs over 800 sq ft