San Diego allows an ADU of up to 1,200 sq ft with no parking and waives its development impact fees for ADUs. Since August 22, 2025, outside the Coastal Zone, a single-family lot can have one JADU, one converted ADU and one new ADU, ADUs can be sold as condos, and the ADU Home Density Bonus is capped at 4 to 6 total ADUs depending on lot size.
Last verified: November 10, 2026
San Diego went further than state law with a local density bonus that let some lots carry far more ADUs than the state requires. In 2025 the city pulled that bonus back. If you are building one or two ADUs on a single-family lot, the reforms barely touch you. If you were planning a bonus project, they change the math.
What Changed for San Diego ADU Permits in 2026
The city’s 2025 ADU and JADU amendments took effect August 22, 2025, outside the Coastal Zone, according to DSD’s regulatory updates page. For a single-family lot, they confirm one JADU, one converted ADU and one detached or attached ADU. ADUs can now be sold as individual condominiums, except bonus ADUs and Housing Commission funded units while their deed restrictions run. Detached ADUs in single-family zones are limited to two stories, and ADUs in high or very high fire hazard zones need four-foot side and rear setbacks.
Two more updates matter. A July 2026 Land Development Code update applies outside the Coastal Zone. And state law changed on January 1, 2026: SB 543 measures size by interior livable space and sets a 15-business-day completeness check, and AB 1154 limits JADU owner occupancy to units that share sanitation with the house.
What San Diego Allows
| Rule | San Diego | Source |
|---|---|---|
| Units on a single-family lot | One JADU, one converted ADU and one new attached or detached ADU (August 2025 amendments) | DSD regulatory updates |
| Maximum size | 1,200 sq ft; 800 sq ft if the lot already exceeds the zone’s floor area ratio | DSD ADU/JADU page |
| Height | Detached ADUs in single-family zones limited to two stories | DSD regulatory updates |
| Parking | None required, and none to replace a converted garage | DSD ADU/JADU page |
| Fees waived | Development Impact Fees, Facility Benefit Assessment fees and General Plan Maintenance fees | DSD ADU/JADU page |
| Rentals | No terms under 31 consecutive days | DSD ADU/JADU page |
| Fire zones | Four-foot side and rear setbacks in high and very high fire hazard severity zones | DSD regulatory updates |
| Separate sale | Allowed as condos, except bonus and Housing Commission funded ADUs during their restrictions | DSD regulatory updates |
The ADU Home Density Bonus After the Reforms
The bonus lets you add ADUs beyond state law if some are deed-restricted affordable through the San Diego Housing Commission. Since August 2025:
- Unit caps, including state-law ADUs: 4 on lots up to 8,000 sq ft, 5 on lots of 8,001 to 10,000 sq ft, and 6 on larger lots.
- Zones: no longer available in several RS-1 zones and RS-11, unless the site is in a high or highest resource area.
- Fire access: in high fire hazard zones, the lot must front a public street with two evacuation routes, not a cul-de-sac.
- Parking: one space per bonus ADU outside a Transit Priority Area.
- Sprinklers: required in bonus and affordable ADUs.
- Community Enhancement Fee: applies to bonus and affordable ADUs under 750 sq ft.
How the San Diego ADU Permit Process Works
- Pick a plan source. A custom design, or permit-ready plans from the County of San Diego or Encinitas’s PRADU program, submitted to city standards.
- Submit digitally under Information Bulletins 152 and 400.
- Pay review fees (Information Bulletin 501) and school fees (Information Bulletin 146).
- Respond to corrections. Under SB 543, comments on resubmittal are limited to items from the first check.
- Get the permit and pass inspections (Information Bulletins 153 and 120).
To legalize an existing unpermitted unit, see Information Bulletin 242 and our AB 2533 guide.
Frequently Asked Questions
How big can an ADU be in San Diego?
Up to 1,200 sq ft, or 800 sq ft if the lot is already over the zone’s floor area ratio.
Do I need parking for an ADU in San Diego?
No, unless it is a bonus ADU outside a Transit Priority Area, which needs one space under the 2025 reforms.
Can I sell my ADU separately in San Diego?
Yes, as a condominium since the August 2025 amendments, except bonus ADUs and Housing Commission funded ADUs while their deed restrictions last.
What fees does San Diego waive for ADUs?
Development Impact Fees, Facility Benefit Assessment fees and General Plan Maintenance fees. School fees and permit fees still apply.
Do the 2025 reforms apply in the Coastal Zone?
Not yet for the August 2025 package; Coastal Zone changes need California Coastal Commission certification. Check with DSD for your parcel.
Sources
- City of San Diego, Accessory and Junior Accessory Dwelling Units: https://sandiego.gov/department/companionjunior-units
- City of San Diego Development Services, Regulatory Updates: https://www.sandiego.gov/development-services/regulatory-updates
For the state rules, see our California ADU law guide. For budgets, see our San Diego ADU cost guide and our San Diego ADU builders.
This page is general information, not legal advice. Confirm current rules with San Diego DSD before you design or apply.
Nearby cities
Permit rules and timelines in other California cities we cover.
Berkeley
8 to 12 weeks
Campbell
5 to 14 weeks
Cupertino
4 to 20 weeks
Long Beach
Same day to 8 weeks
Los Altos
3 to 9 weeks
Los Angeles
4 to 16 weeks
Los Gatos
4 to 16 weeks
Riverside
1 to 12 weeks
Sacramento
60 days after a complete application (state deadline); 30 days with a pre-approved plan
San Francisco
60 days after a complete application (State program)
San Jose
Same day (preapproved plan) to 26 weeks (custom)
Santa Clara
5 to 16 weeks
Saratoga
6 to 18 weeks
Sunnyvale
Over-the-counter review by appointment for single-story projects of 800 sq ft or less; otherwise 21-day first review and 14-day resubmittals, plus 2 to 4 weeks for the Planning permit on new ADUs over 800 sq ft