Montana's SB 528 (2023), codified at MCA 76-2-345, requires every city and town with zoning to allow at least one ADU by right on any lot with a single-family home, capped at the lesser of 1,000 sq ft or 75% of the house, with no owner-occupancy rule, no added parking, no impact fees and an application fee of at most $250. SB 532 (2025, MCA 76-2-215) extended the same rule to zoned counties.
Last verified: November 10, 2026 against MCA 76-2-345 and 76-2-215 on the Montana Code Annotated site, SB 532 (2025) enrolled text, the City of Billings code interpretation of March 11, 2025, and reporting on the Montana Supreme Court's 2024 MAID decision.
Montana’s ADU Law in One Paragraph
Montana has one of the strongest ADU laws in the country, and it is short. SB 528 (2023 Session Laws, chapter 502) added MCA 76-2-345, which requires every incorporated city, town and consolidated city-county that zones land to allow at least one ADU by right on any lot with a single-family home. Local rules that conflicted with it became void on January 1, 2024. In 2025, SB 532 (chapter 619) added MCA 76-2-215, which applies the same rule to counties that zone, with noncompliant county rules void after October 1, 2025. Neither law lets a local government require owner occupancy, extra parking, impact fees or a restrictive covenant, and the application fee is capped at $250. A group of homeowners challenged SB 528 in court, but the Montana Supreme Court reversed the injunction that had blocked it in 2024, and the law is in force.
What Montana’s ADU Law Actually Says
Cities and towns (MCA 76-2-345)
- One ADU by right. At least one ADU on any lot or parcel with a single-family home. It can be attached, detached or internal. “By right” means no public hearing, variance, conditional use permit, special permit or other discretionary approval, only a check that the site plan conforms to zoning.
- Size. An attached or detached ADU can be capped at no less than the lesser of 75% of the house’s gross floor area or 1,000 sq ft. The statute sets no cap for an internal ADU.
- What a city may not require:
- Extra parking, or a fee in lieu of parking.
- A design, roof pitch or finish materials that match the house.
- Owner occupancy of either unit.
- A family, marital or employment relationship between occupants.
- Impact fees on ADU construction.
- Street improvements, except repairing streets the construction disturbs.
- Height, setback, minimum lot size, lot coverage or frontage rules stricter than for the house.
- A restrictive covenant as a condition of the permit (private parties can still agree to one).
- Fees. A one-time application fee of up to $250 per ADU, plus the city’s usual building fees.
- What a city may still do. Regulate short-term rentals; require a will-serve letter from the city water and sewer systems; enforce building, fire and health codes; and adopt rules that are more permissive than the statute.
- Deadline. A city that had not adopted conforming rules by January 1, 2024 must review ADUs under the statute directly, and conflicting ordinances are void.
Counties (MCA 76-2-215, SB 532 of 2025)
Counties that exercise zoning powers must follow the same rules: one ADU by right on any lot with a single-family home, no owner occupancy, no matching design, no impact fees, no stricter dimensional standards, no required covenant, and a $250 application fee cap. County rules that did not comply became void after October 1, 2025. The county section sets no numeric size cap and does not mention parking. It also gives ADUs on lots already served by public water and wastewater a 15-day expedited sanitation review by the Department of Environmental Quality, a provision that ends September 30, 2029.
Does Montana’s ADU Law Apply to You?
- Is your lot in a city, a town or a zoned county? If yes, and there is a single-family home on it, the state guarantees one ADU. Unzoned county land has no zoning barrier to begin with, though sanitation review still applies.
- Attached or detached? Plan for 1,000 sq ft or 75% of the house, whichever is less, unless your city allows more.
- Do you live on site? It does not matter. Owner occupancy cannot be required.
- Private covenants? The statute stops a city or county from requiring one, but it does not void covenants you or a prior owner already agreed to. Check your HOA documents.
- Planning a short-term rental? Your city or county may regulate or bar it.
How Montana Cities Apply It
| City | Status | Key local rules we could confirm | Source | Our guide |
|---|---|---|---|---|
| Billings | Code interpretation issued March 11, 2025 | One ADU allowed in the N1, N2 and N3 zones; local special review, owner occupancy, deed restriction, design, recording and extra parking rules declared void; detached up to 75% of the house or 1,000 sq ft, attached up to 80% or 1,000 sq ft; building permit required; private covenants still apply | City of Billings Zoning Coordinator interpretation | No guide yet |
| Missoula, Bozeman, Great Falls, Helena, Kalispell | Covered by MCA 76-2-345 | Not read from official sources as of November 10, 2026 | None read | No guide yet |
Billings shows how the law works in practice: the city did not wait to rewrite its code, it simply stopped enforcing the parts the statute voided.
The Court Challenge
Montanans Against Irresponsible Densification (MAID), a group of single-family homeowners, sued over SB 528 and other 2023 housing laws, and a Gallatin County judge blocked SB 528 and the duplex law SB 323 in December 2023. The Montana Supreme Court reversed that injunction 5-0 in September 2024, finding the plaintiffs had offered only generalized fears of harm. The laws took effect, and the remaining claims went back to the district court. As of November 10, 2026, we found no ruling that blocks MCA 76-2-345.
What a Montana ADU Costs
The statute caps several costs: no impact fees, no parking spaces or in-lieu fees, no street improvements and a $250 ceiling on the ADU application fee. Building permit and utility connection fees still apply.
We do not have Montana construction cost data in our cost engine yet, so we are not putting a number on this page. For a starting point, see our ADU cost guides, the detached ADU guide and the garage conversion guide, and treat out-of-state numbers as a range, not a quote.
Step by Step for a Montana ADU
- Confirm you are in a city, town or zoned county, and that the lot has a single-family home.
- Get a will-serve letter from the city water and sewer systems if the city asks for one.
- Size the unit within the lesser of 1,000 sq ft or 75% of the house (detached or attached).
- Apply for the ADU approval and building permit. Expect a site plan check, not a hearing, and an ADU application fee of no more than $250.
- Push back on voided conditions. A covenant, owner-occupancy affidavit, matching design or extra parking space cannot be required.
- Check short-term rental rules before you list the unit.
Common Mistakes With Montana’s ADU Law
- Assuming an HOA covenant is void. The law bars governments from requiring covenants; it does not cancel private ones.
- Building larger than 1,000 sq ft. That is the ceiling a city may set for attached and detached units, and many will.
- Paying an impact fee. Cities and counties cannot charge one on ADU construction.
- Reading old local code. Many city codes still carry voided rules; Billings published a list of what it no longer enforces.
How Montana Compares
Montana’s law is close to Washington’s HB 1337 and stronger than its neighbors’. Idaho’s 2026 law covers only cities over 10,000, and Utah lets cities require owner occupancy. For every state, see our guide to which states allow ADUs.
Frequently Asked Questions
Are ADUs allowed in Montana?
Yes. Every city, town and zoned county must allow at least one ADU by right on any lot with a single-family home under MCA 76-2-345 and 76-2-215.
How big can an ADU be in Montana?
A city can cap an attached or detached ADU at the lesser of 1,000 sq ft or 75% of the house, but not lower. Cities may allow more.
Do I have to live on the property to build an ADU in Montana?
No. Cities and counties cannot require owner occupancy of either the house or the ADU.
How much does an ADU permit cost in Montana?
The ADU application fee is capped at $250, and impact fees are banned. Your city’s usual building permit fees still apply.
Does the Montana ADU law apply to counties?
Yes, since SB 532 (2025). Counties that zone must allow one ADU by right, and noncompliant county rules became void after October 1, 2025.
Was the Montana ADU law struck down?
No. A district court blocked it in December 2023, but the Montana Supreme Court reversed that injunction in September 2024, and the law is in force.
Sources
- MCA 76-2-345, Accessory dwelling units (cities): https://mca.legmt.gov/bills/mca/title_0760/chapter_0020/part_0030/section_0450/0760-0020-0030-0450.html
- MCA 76-2-215, Accessory dwelling units (counties): https://mca.legmt.gov/bills/mca/title_0760/chapter_0020/part_0020/section_0150/0760-0020-0020-0150.html
- Montana Legislature, SB 528 (2023): https://archive.legmt.gov/bills/2023/billhtml/SB0528.htm
- City of Billings, Where an Accessory Dwelling Unit is allowed by right (March 11, 2025): https://billingsmt.gov/DocumentCenter/View/53514/Where-an-Accessory-Dwelling-Unit-is-allowed-by-right-March-11-2025
- Explore Big Sky, Montana Supreme Court reverses judge’s decision that blocked residential zoning laws (September 2024): https://www.explorebigsky.com/?p=57537
Disclaimer
This page is general information, not legal advice. Confirm the current rules with your city or county planning office before you design or apply.